Guidance applicable to the program to allocate environmental justice solar and wind capacity limitation
The IRS today released聽聽providing procedural and clarifying guidance applicable to the program under section 48(e) to allocate environmental justice solar and wind capacity limitation with respect to certain solar and wind facilities placed in service in connection with low-income communities鈥攅stablished under H.R. 5376 (commonly called the 鈥淚nflation Reduction Act of 2022鈥� (IRA))鈥攆or the 2024 program year.聽The program provides an increase of 10% or 20% to the investment tax credit rate available under section 48 for taxpayers (or tax-exempt or government entities) that receive an allocation under the program.
The IRS released聽聽in August 2023, providing procedural and clarifying guidance applicable to the program. Rev. Proc. 2024-19 provides the process for the program for 2024, and solely with respect to the 2024 program year, supersedes Rev. Proc. 2023-27.
Rev. Proc. 2024-19 provides important clarifying changes to the application, documentation, and lottery procedures applicable to the 2024 program year. In addition, it describes how the capacity limitation for the 2024 program year will be divided across the facility categories described in Treas. Reg. 搂搂 48(e)(2)(A)(iii) and 1.48(e)-1(b)(2), the Category 1 sub-reservation described in Treas. Reg. 搂 1.48(e)-1(i)(1), and the additional selection criteria application options described in Treas. Reg. 搂 1.48(e)-1(h).
Read a related IRS release鈥斅�(March 29, 2024)
The U.S. Treasury Department and IRS launched the program in February 2023 under Notice 2023-17, which provided initial program guidance for potential applicants for allocations of calendar year 2023 capacity limitation.
Treasury and the IRS then published聽proposed regulations聽in June 2023, supplementing the guidance provided in Notice 2023-17 to outline the specific application procedures, additional allocation criteria, and applicable definitions, among other information, necessary to submit an application to request an allocation of the capacity limitation for calendar year 2023 under the program.聽
The proposed regulations were finalized in August 2023, with the聽聽providing the four project categories under which facilities apply for an allocation, and the increase of either 10% or 20% associated with a project category.聽
Additionally, the final regulations: